Forecast cost adds the cost posted, the open commitments and the estimate to complete. Margin here leaves out overhead.
Ask a follow-up
The list
Rebuild phase job
Customer
Authorized contract
Authorized cost budget
Cost posted
Open commitments
Estimate to complete
Forecast cost
Planned margin
Forecast margin
Supplements not yet approved
EV-R07
Pellhaven Apartments
$72,000
$42,000
$32,000
$17,000
$8,000
$57,000
41.7%
20.8%
$6,000
QP-R08
Fennelcroft Business Court
$90,000
$58,000
$40,000
$18,000
$7,000
$65,000
35.6%
27.8%
$4,000
CB-R09
Ambersley residence
$50,000
$32,000
$22,000
$10,000
$5,000
$37,000
36%
26%
$2,500
Options to consider
Review the remaining cost forecast for EV-R07
Its forecast is $15,000 over the authorized cost budget, a margin of 20.8% against 41.7% planned. Check commitments and the estimate to complete with the project lead.
Your rebuild project lead
Suggested by Oct 8
Add to my plan
Check the open commitments on EV-R07
Confirm that costs already posted have left the open commitments, and walk the estimate to complete with the project lead.
Your rebuild project lead
Suggested by Oct 8
Add to my plan
How we know this
As of Oct 1, 2026
The math
Forecast cost adds the cost posted, the open commitments and the estimate to complete. A commitment already posted leaves the open balance. A supplement not yet approved does not raise the contract. Margin here leaves out overhead; it is not profit earned or a decision about what the carrier will pay.
The records
18 records from your files are behind this answer.
EV-R07, Pellhaven Apartments (5 of 6 records shown)
Cost posted, plus open commitments, plus the estimate to complete, compared with the authorized cost budget. A supplement not yet approved does not raise the contract. Margin here leaves out overhead and is not profit earned.