How do rebuild forecast costs compare with authorized budgets?
3rebuilds
$27,000forecast over budget
Active rebuild forecasts are $27,000 over their authorized cost budgets
EV-R07 is forecast at a margin of 20.8%, against 41.7% planned. Supplements not yet approved are left out of the contract.
Worth watchingAs of Oct 1, 2026
Forecast cost against authorized budget
Separate from past due invoices and from completed work waiting for an invoice.
Forecast cost
Authorized cost budget
Show as a table
Forecast cost against authorized budget
Customer
Forecast cost
Authorized cost budget
Pellhaven Apartments
$57,000
$42,000
Fennelcroft Business Court
$65,000
$58,000
Ambersley residence
$37,000
$32,000
What this means
Forecast cost adds the cost posted, the open commitments and the estimate to complete. Margin here leaves out overhead.
Ask a follow-up
The list
Rebuild phase job
Customer
Authorized contract
Authorized cost budget
Cost posted
Open commitments
Estimate to complete
Forecast cost
Planned margin
Forecast margin
Supplements not yet approved
EV-R07
Pellhaven Apartments
$72,000
$42,000
$32,000
$17,000
$8,000
$57,000
41.7%
20.8%
$6,000
QP-R08
Fennelcroft Business Court
$90,000
$58,000
$40,000
$18,000
$7,000
$65,000
35.6%
27.8%
$4,000
CB-R09
Ambersley residence
$50,000
$32,000
$22,000
$10,000
$5,000
$37,000
36%
26%
$2,500
Options to consider
Review the remaining cost forecast for EV-R07
Its forecast is $15,000 over the authorized cost budget, a margin of 20.8% against 41.7% planned. Check commitments and the estimate to complete with the project lead.
Your rebuild project lead
Suggested by Oct 8
Add to my plan
Check the open commitments on EV-R07
Confirm that costs already posted have left the open commitments, and walk the estimate to complete with the project lead.
Your rebuild project lead
Suggested by Oct 8
Add to my plan
How we know this
As of Oct 1, 2026
The math
Forecast cost adds the cost posted, the open commitments and the estimate to complete. A commitment already posted leaves the open balance. A supplement not yet approved does not raise the contract. Margin here leaves out overhead; it is not profit earned or a decision about what the carrier will pay.
The records
18 records from your files are behind this answer.
EV-R07, Pellhaven Apartments (5 of 6 records shown)
Cost posted, plus open commitments, plus the estimate to complete, compared with the authorized cost budget. A supplement not yet approved does not raise the contract. Margin here leaves out overhead and is not profit earned.